Practice of RACI Matrix in an organization

RACI Matrix or linear responsibility chart (LRC) can also be called as a responsibility assignment matrix. A useful tool to classify the sequence of work in a process and the roles and responsibilities for each of the task

Practice of RACI Matrix in an organizationPractice of RACI Matrix in an organization

Practice of RACI Matrix in an organization

R – stands for (Responsibility) – Someone who is to carry out the task.

A – stands for (Accountability) – someone who is the final authority and accountability for the completion of the task.

C – stands for (Consulted) – someone who needs to be consulted during the carrying out of the task.

I – stands for (Informed) – someone who needs to be kept informed after the task has been completed.

RACI Matrix – Mapping the “As Is”

Step – 01

Advertisement

List down the tasks of the work process in sequence.

Step – 02

Identify all the relevant stakeholders involved in the process.

Step – 03

For each of tasks, identify who is responsible, accountable, consulted, and informed.

Step – 04

Put in remarks to explain the roles and responsibilities if necessary.

Once a process has been analyzed and improvements made, a new “should be” RACI matrix can be developed.

Illustration / Example of RACI Matrix

Sample RACI Matrix for Recruitment and Selection process

Advertisement
Process Task HOD HR Dept. Line manager Remarks
1.      Make hiring request C I R/A ·         Line manager is responsible and accountable for make hiring request to HOD.

·         HOD is to be consulted and HR department is to kept informed.

2.      Approve hiring request R / A I C / I ·         HOD is responsible and accountable for approving

·         Line manager may be consulted and both HR Department and line manager is to be informed.

3.      Update job description  – I R / A ·         Line manager is responsible and accountable for updating the job description and HR Department is to be informed.
4.      Put up job advertisement R /A I ·         HR Department is responsible and accountable and line manager is to be informed

RACI Matrix – Additional Guidelines
  • Minimize “R”s . Too many “R”s may cause bottlenecks in a specific task.
  • Limit to only one ‘A’ . Multiple ‘A’s may cause confusion as to who is in charged and accountable.
  • Minimum ‘C’s . Too many ‘C’s may cause bottlenecks in a specific task. However, make sure all necessary stakeholders are consulted.
  • Identify all ‘I’s . Ensure all stakeholders who need to be kept informed are identified so that related follow up tasks can be carried out.